Details of investment made and financial assistance received by Jalandhar CETP towards establishment. | |||||||||
Year | Major Component | Design Capacity | Project Cost (Rs. in lakhs) | Funding Agencies And % Contributed | Scheme | Contributions(Rs. in lakhs) | |||
---|---|---|---|---|---|---|---|---|---|
|
|||||||||
1992 | 1st Module of CETP | 1.5 MLD | Established by PSLDC/PSIEC at the time of the carving out of Leather Complex. | Industry PSLDC/PSIEC collected development charges from the industry at the time of allotment of plots. | - |
|
|||
2010 | 2nd Module | 5 MLD | Rs. 16.80 crores then revised to 18.80 crores. | GoI-50% State Govt-50% | ASIDE |
|
The plant is being operated as aerobic system.