Establishment

Establishment

Details of investment made and financial assistance received by Jalandhar CETP towards establishment.
Year Major Component Design Capacity Project Cost (Rs. in lakhs) Funding Agencies And % Contributed Scheme Contributions(Rs. in lakhs)
           
GoIState Govt.Industry
1992 1st Module of CETP 1.5 MLD Established by PSLDC/PSIEC at the time of the carving out of Leather Complex. Industry PSLDC/PSIEC collected development charges from the industry at the time of allotment of plots. -
-Part of the complex development charges-
2010 2nd Module 5 MLD Rs. 16.80 crores then revised to 18.80 crores. GoI-50%
State Govt-50%
ASIDE
840840200

The plant is being operated as aerobic system.